IMG_1712 My book is finally available as an eBook, on Amazon Kindle and on Amazon. I wrote this book to share my experience in how to rescue failing software projects. When I was going through such a situation, I had no one to turn to. My hope is that the information in this book will be useful to those in similar situations. Although the information in the book pertains to software projects, I have come to realize that the techniques can be used in many other situations. I have personally used these techniques in business and technical projects.

You can read more about it here.
My book can be purchased here at Amazon.com.
Amazon Kindle version is available here at Amazon.com


Showing posts with label IT project management. Show all posts
Showing posts with label IT project management. Show all posts

Saturday, April 09, 2011

Requiements capture

Gathering requirements is both an art and a science. There are numerous project templates on the web that can be used to capture or gather project requirements.

It is a science because these templates guide an analyst to gather the user requirements for a project. It is an art because the template only has headings or guidelines. It is a generic template and the analyst has to use common sense and industry knowledge to probe and distill user requirements into a specific, measurable and deliverable requirement.

Most requirements focus on the functional aspect of a project. These are termed "user requirements". These are the functions or use cases the user must have or would like to have delivered through the project.

The architectural requirements are normally done as part of design, or worse still, an after-thought. I define architectural requirements as other requirements not pertaining to the functional aspect of the project. For example, security requirements, performance requirements, scalability and extensibility requirements, availability requirements. From this list alone, you can deduce that the term "user" goes far beyond the business user or the user that specifies the functional use cases. The project team's interaction must now encompass the customer's security team, systems and infrastructure team, application maintenance team.

If requirements capture is viewed in this manner, the project team will begin to identify the various "users" needed for project success and begin building close working relationships with the extended eco-system. The relationships cannot be a one-off relationship. It is an on-going relationship as the project progresses.

Bernard
---------------------------
Save This Page
Copyright © Bernard Ong, 2006-2011.
All Rights Reserved
http://RescueSoftwareProjects.blogspot.com
http://www.bernard-ong.com
http://mrbolt.blogspot.com
http://BuddhismToday.blogspot.com

Friday, April 01, 2011

Reviews are critical in project management!

Core technical skills, software design, writing code are all considered important and critical activities of a project. The perceived "softer" activities such as regular project reviews are considered optional.

This situation is very common in projects. Software design and writing code produces visible results such as the software module or use case that can be viewed and tested. You can't see or view the result of project review. If project reviews are done correctly and properly, and the project progresses without major issues, no one will acknowledge or miss the importance of project reviews. The importance of project reviews are often overlooked.

In my experience, project reviews, if done correctly and properly, keeps the team focused, productive and more importantly, effective. In my opinion, it is a critical activity.

However, how many would agree to this? If the project is on track and progressing well, no one will acknowledge this point. If the project is failing, some may acknowledge this point, others will blame the software design, code quality, coding standards, scope creep. While there is some truth in this, project reviews help prevent major catastrophes and at least, identify and highlight such catastrophe may be on the horizon and the team needs to take corrective action.

Bernard

---------------------------
Save This Page
Copyright © Bernard Ong, 2006-2011.
All Rights Reserved
http://RescueSoftwareProjects.blogspot.com
http://www.bernard-ong.com
http://mrbolt.blogspot.com
http://BuddhismToday.blogspot.com

Monday, March 28, 2011

Deluge of Project Documentation

I have heard of projects where a huge number of project documentation is required. The number of project binders sits proudly on desks and shelves, exuding the aura of importance and completeness.


I have found that nothing can be further from the truth. Many of these documentation took a long time to create, edit and review...and never used again. What a waste of effort and time, time that could be have been put to better use.

However, I do agree that documentation is required. There has to be a balance as to what is essentially required, what is nice to have. Those that are essential to the project will always be referenced, used, corrected, modified to reflect the project's current status.

Documentation should be used as a means to record critical decision points, important design elements and motivation behind the through process.

I do not recommend going overboard with documentation. A careful selection of project documentation will serve the project well during its formative stages, through its operational phases and till it is retired from operation. Add in additional documentation only as needed to serve a critical specific purpose that can be used throughout the project's lifecycle.

Bernard
---------------------------
Save This Page
Copyright © Bernard Ong, 2006-2011.
All Rights Reserved
http://RescueSoftwareProjects.blogspot.com
http://www.bernard-ong.com
http://mrbolt.blogspot.com
http://BuddhismToday.blogspot.com

Sunday, March 20, 2011

Rescue a failing software project?

 Can a failing software project really be rescued?

The answer is YES...with a few qualifications.
Can a failing software project be rescued in the traditional sense? No.

Let me explain.

The word "rescue" is vague. It carries a lot of different expectations and perceptions. To some, "rescue" means saving the project so that it can complete its original objective, on time, on budget. To others, "rescue" means completing the project. Other opinions refer "rescue" to "mercifully" terminating the project.

So you see, rescuing or saving a project is very possible, depending on definition and expectations. But all this is a play on words.

The real question is whether a failing software project can be saved such that the project completes its original objectives and make an attempt to be on time and within the stipulated budget. My honest answer and experience is that sometimes it is possible, at other times it is impossible.

Why impossible?

For example, if a building were built on an extremely weak foundation, or the building plans were drawn out with major defects, the building will be deemed as unsafe and will probably have to be torn down where rectification works will not suffice.

Likewise with software projects. In fact, besides the technical aspects, the more important aspects are expectations of timeline, cost, ego,  and pride. If a failing software project were to be rescued, it has to be looked at from the technical, timeline and cost aspect. If there is too much ego, pride and politics involved, the rescue will never succeed. Maybe it was these softer issues that caused the project failure in the first place.

My humble opinion.

Bernard
---------------------------
Save This Page
Copyright © Bernard Ong, 2006-2011.
All Rights Reserved
http://www.bernard-ong.com
http://mrbolt.blogspot.com
http://RescueSoftwareProjects.blogspot.com
http://BuddhismToday.blogspot.com

Monday, March 08, 2010

Bad project manager?

You may have started a new project or have been managing one for some time. Your project may have slipped, may be delayed a bit or in downright trouble.

Does this mean you are not a good project manager? Not so.

Many factors come into play. Many factors may have been out of your control, although the sage saying is that everything should be in the project manager's control.

Is this really true? What do you think?

I think not. Experienced project managers know that they can control what they can control and only influence what they cannot directly control. For example, inter-departmental politics, vendor politics, customer politics.

The project manager must attempt to influence the situation so that all interested parties move the project in the same direction, which is forward towards the launch date. We all know this doesn't always happen.

So what can we do?

Control what is within your control and influence interested parties. The main point is for the team to keep pushing progress foreward. There will come a point where the project is ready and no matter the politics, the project is simply ready for launch. Nothing else to debate or discuss.

This is easier said than done as it requires skillful management to keep the team morale high and keep the team together.

---------------------------
Save This Page

Copyright © Bernard Ong, 2006-2009.
All Rights Reserved
http://www.bernard-ong.com
http://mrbolt.blogspot.com

Tuesday, December 22, 2009

Managing life and projects

Would you manage your life the way you manage a project? Or rather, would you manage your project the way you manage your life?

Is there a difference? Yes and no. Managing requires skill, expertise and thoughtful planning and execution.

When IT projects are managed, there are lots of flexibility and leeway given to the scope, robustness of testing, and disciplined execution. What if the IT project was to create a system that dealt with life and death situations? how different would that perspective be?

With life and death situations, more careful thought, planning, execution, ensuring all requirements are duly met, robustness and fail overs are included. In many non-critical IT systems, this is not the case. So what if there is a bug here, a failure there? Simply restart the system or simply log the error and rectify it later.

Would you walk into a skyscraper that had been built without a firm foundation, where the developer skimped on materials, had shoddy workmanship, and building approvals were lacking? I think not because your life is at stake the minute you walk into that building and the building could collapse.

If we treat each and every IT project with such a mindset, both the users and vendors will be more careful with scope, requirements, development, testing and eventually, have a system that will meet the end-user's needs.

I'd like to wish all my readers a very Merry Christmas and a Happy new Year 2010. Happy Holidays everyone.

Bernard

---------------------------
Save This Page

Copyright © Bernard Ong, 2006-2009.
All Rights Reserved
http://www.bernard-ong.com
http://mrbolt.blogspot.com

Tuesday, September 15, 2009

Decisions you make, when all the stars in the universe align and a cup of coffee!


What a day! It began like any other day. Within one hour, it was as though all the stars in the universe were aligned. The decisions my wife an I made early in the morning caused the stars in the universe (my universe) align.

Decision #1
------------
My daughter had classes really early this morning. I decided to drive her to school at 6.40am, and head to Starbucks by the beach. I had decided to have Bagel and coffee for breakfast with my wife before getting started on my work.

As luck would have it, we were too early. Yup. At 7.30am, Starbucks was closed. We were sorely disappointed. We stood outside Starbucks for 10 minutes, deciding where we could go to fill our growling hungry stomachs.

Decision #2
-----------
Between going to a hawker centre and a McDonald's by the beach, we decided to have breakfast at McDonalds.

Decision #3
-----------
While at McDonalds, we took 5 minutes to decide on our breakfast. It was a difficult choice because we were set on having bagels. As we were about to place our orders, a voice behind me said, "Why aren't you in Korea?".

Conrad, an old school mate and buddy of mine, had also just dropped by McDonalds for breakfast with his wife after sending their kids to school. He is also one person who would kick me if I did not complete writing my book "How to rescue failing software projects", which I eventually did and got it listed on Amazon! (Believe me, you don't want to be kicked by Conrad!)

What a coincidence. We had a really nice chat, catching up on the latest happenings in his field of work and compared notes on family tips.

It wasn't long before Conrad's sister, Gwen, came roller-blading by. Another coincidence. She teaches in an education centre that my son attends. She also mentioned that another common friend of ours was having breakfast with his wife at another coffee joint.

Adam, the other "common friend", and his wife, came by McDonalds and we all sat around a small table, sipping on coffee while catching up with each other. Adam is the other person who gave me the inspiration to write my book.

While we sat around a table sipping coffee, we didn't talk about business. There were no expectations placed on any of us. We were relaxed and comfortable, sharing our experience and insights freely

What are the chances that a group of friends can get together by being at the same place, at the same time and doing the same thing? All the stars in the universe must have been aligned!

What has this got to do with effectiveness and project management? A lot. It may seem like a simple get-together, but the same concepts learned from this simple setting can be very powerful.

Observation #1
--------------
Simple decisions can determine the outcome of major tasks. If my wife and I hadn't made the decision to have breakfast together at Starbucks, this chain of events wouldn't have happened. It takes one decision to get the ball rolling.

Observation #2
--------------
When one door closes, another opens. If we hadn't made the decision to have breakfast at Starbucks, we wouldn't have had the opportunity to make an alternative decision to have breakfast at McDonalds. If we didn't have breakfast at McDonalds, we wouldn't have met Conrad and Adam with their wives, and Gwen. If my wife and I had breakfast just 10 minutes earlier or 10 minutes later, we wouldn't have had the gathering. A closed door or failed opportunity leads to another open door, provided a decision is made to take action.

Observation #3
--------------
Not all get-togethers or meetings need to be about business. In managing projects, project managers and team members are up to their necks with uncompleted tasks. It does pay to have small breaks, or small celebrations on milestone completions. These breaks and celebrations are just that...real breaks. It should not be done on a pretext of having a break, and end up having a meeting about the project over coffee. It is about building rapport. It is about understanding each other in the team. It is about building camaraderie and friendships. People relate best when they are relaxed and not have expectations put upon them. Especially in project teams where there is always a tight schedule and endless number of tasks, these friendships help the project team to have a higher morale and thus, leading to greater productivity.

I have personally experienced observation #3 when I was in the midst of rescuing projects. No matter how tired we were, we remained a cohesive team, We understood each other better, we could relate to each other's challenges better and we were willing to help each other out. There was a strong "give-and-take" attitude that enabled us to successfully turn projects around. Boundaries and walls within the team were chipped away naturally.

So, do not wait for all the stars in the universe to align before having a cup of coffee. Make that decision to enjoy a simple, freshly brewed, steaming hot cup of coffee with your family, with your team, with your boss, or just by yourself. You never know when and how the stars will align for you.

Bernard



---------------------------
Save This Page

Copyright © Bernard Ong, 2006-2009.
All Rights Reserved
http://www.bernard-ong.com
http://mrbolt.blogspot.com

Sunday, April 12, 2009

What to manage in IT project management?

What is there in an IT project that needs IT project management?

There are so many aspects to project management. Its a complex yet simple subject. Many project managers will have different perspectives as to what is important in IT project management. Project management associations and institutes have differing views as well. Despite these different views, there are common threads that run through each view.

Ironic? No. Just as a situation can be viewed in many different ways, a job can be accomplished in many different ways too.

IT project management encompasses the technical aspects of IT, which is about well designed architectures, well translated and implemented codes. It encompasses good project management practices such as a clear and well thought-out plan and schedule, contracts that are clearly agreed upon, expectations of the end goal well communicated and agreed. THere are many more facets to IT project management.

All these sound logical and usually requires common sense. However, for those who have been involved in IT projects know that "what will go wrong, will". Despite the difficulties, there are always ways to workaround and get the project delivered to expectations and within time and budget.

In each of these facets of IT project management, there are nuances and issues to be addressed. Some are complex issues that go beyond the technical realm. It requires human interaction, negotiation and effectiveness.

An IT project is like an army mission. Many supporting roles are required such as logistics, long range weapons, foot-soldiers, planning on deployment and timing of troop movement, attack and defence plan. All these have to work in tandem. The commander cannot focus on only one aspect and 'hope' that the other aspects of the mission will go well. The commander needs to know each and every aspect well in order to mobilize troops and make necessary adjustments for a successful mission.

Likewise for IT projects. Most project managers I know focus only on areas they are comfortable with, either on the plan and schedule, or technical, or contract. This is where project go awry.

A competent project manager needs to know every aspect of the project well. He may not be fully competent in a certain area, in which case, he needs to engage the helps of his team leads to provide him with accurate information...and go down to the ground to verify. Nothing beats real information from the ground.

When a project manager doesn't manage a project from a holistic perspective, he cannot manage effectively. WHen the project begins to fail, he will not be able to confidently steer the project to a successful completion. THis is one typical cause of project downfall.

Whether in projects or personal life, situations and projects must be looked at in a holistic manner. Neglecting an area can lead to a stagnation or detriment to the project or personal life.

Bernard


---------------------------